Adron Homes & Property Limited

< All Topics
Print

Adron Homes & Property Limited

Standard Operating Procedure (SOP)

Document CON01

Directorate: Construction Directorate 

Title: INITIATION OF INTERNAL PROJECTS
Effective Date: xx/xx/xxxx
Version: 1.0

  1. PURPOSE
    • This SOP defines the structured process for initiating internal construction projects.
    • Internal projects include property developments for in-house purposes, such as:
      • Infrastructure development
      • Assets intended for company use
    • This SOP ensures a structured and compliant approach to initiating internal construction projects while maintaining accountability through the ERP system.
    • Note: This SOP does not apply to customer-based projects or residential/commercial construction for sale.
  2. SCOPE
    • This procedure applies to all internal construction projects managed via the company’s ERP system, ensuring standardized workflows, approvals, and documentation.
  3. RESPONSIBILITIES
    • Project Director (PD): Reviews and approves project feasibility and high level scope
    • Project Manager: Identifies the need for the project, prepares the initial project proposal and submits it for approval.
    • Resident Quantity Surveyor(RSQ): Prepares BOQ for the proposed projects
    • Chairman/Project Executive Committee: Provide final approval for the proposed project
  4. PROCEDURE
    • There are two major types of internal projects procedures  as below :
    • GENERAL INTERNAL PROJECTS
      • General projects are projects that are small in scale and estimated project cost is less than N10 million
      • Project Managers Responsibilities
        • Project Manager (PM) initiates the n project on the ERP using the INTERNAL PROJECT MEMO SCREEN
        • The PM must specify the following among others.
        • Process Type for selection is Internal Project – General
        • Project Name
        • Detailed Project Descriptions
        • Estimated project cost
        • The PM must attach relevant documents including sketch/prototype  drawing.
        • The PM submits the initiating transaction for processing by relevant Project Director (PD)
        • The system notifies the PD by email to treat.
      • Project Director (PD) Responsibilities
        • PD   review, approves and submits for the attention of the Chief Project Director & Design (CPDD)
        • Chief Project Director & Design (CPDD) Responsibilities
        • CPDD   review, approves and submits for the attention of the Resident Quantity Surveyor (RSQ)
      • Quantity Surveyor (RSQ) Responsibilities
        • RSQ prepares BOQ and attaches relevant documents as deemed necessary for the attention of the Chief Project Controller (CPC)
        • RSQ   review, approves and submits for the attention of the Chief Project Controller (CPC)
        • CPC   review, approves and submits for the attention of the Project Executive Committee (PEC)
      • Project Executive Committee (PEC) Responsibilities
        • Members of the PEC include
        • CPDD- chairman
        • CPC
        • PD
        • Group Project Finance Manager (GPFM)
        • PEC members    review while the PEC chairman, CPDD approves on behalf of the PEC  for the attention of the GMD
        • Chairman is notified by the system
      • Chairman’s Responsibilities
        • Chairman reviews and approves.
        • At Final Approval by Chairman
        • System  initiates the following actions
          • Action 1 : system creates the Project ID
          • Action 1 : system send email to the GPFM and CPDD to commence the project activities and payment transactions
      • Project Admin Responsibilities
        • Populate the Project ID as defined as auto-created by the system with more detailed info about the project
    • MAJOR  INTERNAL PROJECTS
      • Major  projects are projects that are large in scale and estimated project cost is more  than N10 million
      • Project Managers Responsibilities
        • Project Manager (PM) initiates the n project  on the ERP using the INTERNAL PROJECT MEMO SCREEN
        • The PM must specify the following among others
          • Process Type for selection is Internal Project – Major
          • Project Name
          • Detailed Project Descriptions
          • Estimated project cost
        • The PM must attach relevant documents including sketch/prototype drawing.
        • The PM submits the initiating transaction for processing by relevant Project Director (PD)
        • The system notifies the PD by email to treat.
      • Project Director (PD) Responsibilities
        • PD   review, approves and submits for the attention of the Chief Project Director & Design (CPDD)
        • Chief Project Director & Design (CPDD) Responsibilities
        • CPDD   review, approves and submits for the attention of the Head of Studio  (HS)
      • Head of Studio Responsibilities
        • Head of studio (HS) prepares full drawings of the project.
        • Architects attach the full drawings to the system.
        • HS review, approves and submits for the attention of the Resident QS
      • Quantity Surveyor (RSQ) Responsibilities
        • RSQ prepares BOQ and attaches relevant documents as deemed necessary for the attention of the Chief Project Controller (CPC)
        • RSQ   review, approves and submits for the attention of the Chief Project Controller (CPC)
        • CPC   review, approves and submits for the attention of the Project Executive Committee (PEC)
      • Project Executive Committee (PEC) Responsibilities
        • Members of the PEC include:
          • CPDD- chairman
          • CPC
          • PD
          • Group Project Finance Manager (GPFM)
        • PEC members review while the PEC chairman, CPDD approves on behalf of the PEC for the attention of the GMD
        • GMD is notified by the system
      • Chairman’s  Responsibilities
        • Chairman reviews and approves.
        • At Final Approval by Chairman
        • System  initiates the following actions
          • Action 1 : system creates the Project ID 
          • Action 1 : system send email to the GPFM and CPDD to commence the project activities and payment transactions
      • Project Admin Responsibilities
        • Populate the Project ID as defined as auto-created by the system with more detailed info about the project.
      • Kickoff Meeting
        • The Project Manager conducts a kickoff meeting with stakeholders to:
          • Confirm scope, deliverables, and timelines
          • Assign roles and responsibilities
          • Define communication protocols
      • Documentation & Compliance
        • The following documents must be uploaded to the ERP system:
          • Feasibility report
          • BOQ approval
          • Regulatory permits (if applicable)
  5. Key Performance Indicators (KPIs)
    • Time from PIR submission to approval
    • Compliance with ERP documentation requirements
    • Adherence to BOQ  budget and scope during initiation