Document CON01
Directorate: Construction Directorate
Title: INITIATION OF INTERNAL PROJECTS
Effective Date: xx/xx/xxxx
Version: 1.0
- PURPOSE
- This SOP defines the structured process for initiating internal construction projects.
- Internal projects include property developments for in-house purposes, such as:
- Infrastructure development
- Assets intended for company use
- This SOP ensures a structured and compliant approach to initiating internal construction projects while maintaining accountability through the ERP system.
- Note: This SOP does not apply to customer-based projects or residential/commercial construction for sale.
- SCOPE
- This procedure applies to all internal construction projects managed via the company’s ERP system, ensuring standardized workflows, approvals, and documentation.
- RESPONSIBILITIES
- Project Director (PD): Reviews and approves project feasibility and high level scope
- Project Manager: Identifies the need for the project, prepares the initial project proposal and submits it for approval.
- Resident Quantity Surveyor(RSQ): Prepares BOQ for the proposed projects
- Chairman/Project Executive Committee: Provide final approval for the proposed project
- PROCEDURE
- There are two major types of internal projects procedures as below :
- GENERAL INTERNAL PROJECTS
- General projects are projects that are small in scale and estimated project cost is less than N10 million
- Project Managers Responsibilities
- Project Manager (PM) initiates the n project on the ERP using the INTERNAL PROJECT MEMO SCREEN
- The PM must specify the following among others.
- Process Type for selection is Internal Project – General
- Project Name
- Detailed Project Descriptions
- Estimated project cost
- The PM must attach relevant documents including sketch/prototype drawing.
- The PM submits the initiating transaction for processing by relevant Project Director (PD)
- The system notifies the PD by email to treat.
- Project Director (PD) Responsibilities
- PD review, approves and submits for the attention of the Chief Project Director & Design (CPDD)
- Chief Project Director & Design (CPDD) Responsibilities
- CPDD review, approves and submits for the attention of the Resident Quantity Surveyor (RSQ)
- Quantity Surveyor (RSQ) Responsibilities
- RSQ prepares BOQ and attaches relevant documents as deemed necessary for the attention of the Chief Project Controller (CPC)
- RSQ review, approves and submits for the attention of the Chief Project Controller (CPC)
- CPC review, approves and submits for the attention of the Project Executive Committee (PEC)
- Project Executive Committee (PEC) Responsibilities
- Members of the PEC include
- CPDD- chairman
- CPC
- PD
- Group Project Finance Manager (GPFM)
- PEC members review while the PEC chairman, CPDD approves on behalf of the PEC for the attention of the GMD
- Chairman is notified by the system
- Chairman’s Responsibilities
- Chairman reviews and approves.
- At Final Approval by Chairman
- System initiates the following actions
- Action 1 : system creates the Project ID
- Action 1 : system send email to the GPFM and CPDD to commence the project activities and payment transactions
- Project Admin Responsibilities
- Populate the Project ID as defined as auto-created by the system with more detailed info about the project
- MAJOR INTERNAL PROJECTS
- Major projects are projects that are large in scale and estimated project cost is more than N10 million
- Project Managers Responsibilities
- Project Manager (PM) initiates the n project on the ERP using the INTERNAL PROJECT MEMO SCREEN
- The PM must specify the following among others
- Process Type for selection is Internal Project – Major
- Project Name
- Detailed Project Descriptions
- Estimated project cost
- The PM must attach relevant documents including sketch/prototype drawing.
- The PM submits the initiating transaction for processing by relevant Project Director (PD)
- The system notifies the PD by email to treat.
- Project Director (PD) Responsibilities
- PD review, approves and submits for the attention of the Chief Project Director & Design (CPDD)
- Chief Project Director & Design (CPDD) Responsibilities
- CPDD review, approves and submits for the attention of the Head of Studio (HS)
- Head of Studio Responsibilities
- Head of studio (HS) prepares full drawings of the project.
- Architects attach the full drawings to the system.
- HS review, approves and submits for the attention of the Resident QS
- Quantity Surveyor (RSQ) Responsibilities
- RSQ prepares BOQ and attaches relevant documents as deemed necessary for the attention of the Chief Project Controller (CPC)
- RSQ review, approves and submits for the attention of the Chief Project Controller (CPC)
- CPC review, approves and submits for the attention of the Project Executive Committee (PEC)
- Project Executive Committee (PEC) Responsibilities
- Members of the PEC include:
- CPDD- chairman
- CPC
- PD
- Group Project Finance Manager (GPFM)
- PEC members review while the PEC chairman, CPDD approves on behalf of the PEC for the attention of the GMD
- GMD is notified by the system
- Members of the PEC include:
- Chairman’s Responsibilities
- Chairman reviews and approves.
- At Final Approval by Chairman
- System initiates the following actions
- Action 1 : system creates the Project ID
- Action 1 : system send email to the GPFM and CPDD to commence the project activities and payment transactions
- Project Admin Responsibilities
- Populate the Project ID as defined as auto-created by the system with more detailed info about the project.
- Kickoff Meeting
- The Project Manager conducts a kickoff meeting with stakeholders to:
- Confirm scope, deliverables, and timelines
- Assign roles and responsibilities
- Define communication protocols
- The Project Manager conducts a kickoff meeting with stakeholders to:
- Documentation & Compliance
- The following documents must be uploaded to the ERP system:
- Feasibility report
- BOQ approval
- Regulatory permits (if applicable)
- The following documents must be uploaded to the ERP system:
- Key Performance Indicators (KPIs)
- Time from PIR submission to approval
- Compliance with ERP documentation requirements
- Adherence to BOQ budget and scope during initiation