Standard Operating Procedure (SOP)
Document CON02
Directorate: Construction Directorate
Effective Date: xx/xx/xxxx
Version: 1.0
- PURPOSE
- This SOP defines the structured process for authorizing and processing the first payment of construction contracts within the Construction Directorate.
- It ensures compliance with the company’s delegation of authority (DoA), internal controls, and contractual obligations while leveraging the ERP system for workflow efficiency.
- SCOPE
- This procedure applies to all construction contracts managed by the Construction Directorate of ADRON, where payments are processed through the ERP system.
- KEY ROLES & RESPONSIBILITIES
- Project Manager (PM): Initiates the first payment request and ensures all supporting documents are attached
- Resident Quantity Surveyor (RQS): Provides supporting documentation (BOQ, milestone verification, work completion evidence).
- Project Director (PD): Reviews and approves the payment request before submission for further processing
- Legal Officers: Ensure the contract is duly executed and validate compliance with contractual terms.
- Project Accountant: Confirms fulfilment of pre-payment conditions and processes payment in the ERP system.
- PROCEDURE
- Initiation of First Payment Request
- The Project Manager (PM) initiates, prepares and submits a First Payment Request in the ERP system, including:
- Copy of the executed contract
- ERP Navigation
- Construction Project Module >>Payable Booking Process> Project Payable Booking
- PM must specify the following among others.
- Contract Type as Performance Certificate Based
- 1st Payment amount
- Net contract sum
- The PM must attach relevant documents including 1st payment advance invoice from contractor.
- The PM must select relevant BOQ summary Items while the system computes the relevant withholding tax as may have been set up, if any?
- At submission, the transaction moves to the RQS for reviews
- The Project Manager (PM) initiates, prepares and submits a First Payment Request in the ERP system, including:
- Initiation of First Payment Request
- Resident Quantity Surveyor (RQS) certification of completed works (measured works, milestone verification).
- Any additional supporting documents (e.g., BOQ, advance payment guarantee, insurance certificates).
- RQS validates bills and attaches relevant documents as deemed necessary.
- RQS review, approves and submits for the attention of the Project Controller (CPC)
- Approval Process
- The Project Director (PD) reviews the payment request for accuracy and completeness.
- If compliant, the PD approves the request in the ERP system.
- If non-compliant, the request is returned to the PM for correction
- Legal & Contractual Validation
- Legal Officers verify:
- The contract is duly executed.
- Payment terms comply with the agreement (e.g., advance payment conditions, guarantees).
- No legal impediments to payment exist
- Once approved, the document moves to Internal Control Officer.
- Legal Officers verify:
- Internal Control Officer
- Internal Control verify:
- The contract is duly executed.
- Payment terms comply with the agreement (e.g., advance payment conditions, guarantees).
- No legal impediments to payment exist.
- Internal Control verify:
- Pre-Payment Validation by Finance
- The Project Accountant confirms:
- The contract is registered in the ERP system.
- All pre-payment conditions (e.g., bank guarantees, insurances) are fulfilled.
- The payment amount aligns with the DoA limits
- Group Project Finance Manager (GPFM) Responsibilities
- Group Project Finance Manager (GPFM) review and validate all attached documents.
- Subjective Final Approval – DOA
- Approvals Limits
- Less than N5 m– GPFM
- Greater than – N5m – Chairman
- At final approval, the system auto-creates the e-payment voucher for the approved net payable amount.
- Group Project Finance Manager (GPFM) review and validate all attached documents.
- Construction Treasury Responsibilities
- Project Accountant process e-payment vouchers and submits for cheque or transfer approval on ERP.
- Bill Payment Approval
- Project Accountant and Internal Control
- GPFM and Zonal Internal Control
- Zonal Internal Control Officer signs cheque and e-payment voucher on ERP at the same time
- Zonal Project Accountant or GPFM signs cheque and e-payment voucher on ERP at the same time
- Project Accountant process e-payment vouchers and submits for cheque or transfer approval on ERP.
- The Project Accountant confirms:
- ERP Processing & Payment Release
- Once all approvals are secured, the Project Accountant processes the payment in the ERP system.
- The system enforces authorization limits and maintains an audit trail.
- Payment is released to the contractor as per agreed terms (e.g., bank transfer).
- Compliance & Documentation
- Delegation of Authority (DoA): All approvals must comply with the company’s DoA matrix.
- ERP Archiving: All supporting documents (contracts, certifications, approvals) must be uploaded to the ERP for audit purposes.
- Audit Trail: The ERP system logs all actions (submission, approvals, rejections) for transparency.
- Exceptions & Dispute Resolution
- If discrepancies arise (e.g., incomplete documentation, non-compliance with contract terms), the request is escalated to the Finance & Legal Departments for resolution before reprocessing