NEW CONTRACT 1ST PAYMENTS

Adron Homes & Property Limited

Standard Operating Procedure (SOP)

Document CON02

Directorate: Construction Directorate 

Effective Date: xx/xx/xxxx
Version: 1.0

  1. PURPOSE
    • This SOP defines the structured process for authorizing and processing the first payment of construction contracts within the Construction Directorate.
    • It ensures compliance with the company’s delegation of authority (DoA), internal controls, and contractual obligations while leveraging the ERP system for workflow efficiency.
  2. SCOPE
    • This procedure applies to all construction contracts managed by the Construction Directorate of ADRON, where payments are processed through the ERP system.
  3. KEY ROLES & RESPONSIBILITIES
    • Project Manager (PM): Initiates the first payment request and ensures all supporting documents are attached
    • Resident Quantity Surveyor (RQS): Provides supporting documentation (BOQ, milestone verification, work completion evidence).
    • Project Director (PD): Reviews and approves the payment request before submission for further processing
    • Legal Officers: Ensure the contract is duly executed and validate compliance with contractual terms.
    • Project Accountant: Confirms fulfilment of pre-payment conditions and processes payment in the ERP system.
  4. PROCEDURE
    • Initiation of First Payment Request
      • The Project Manager (PM) initiates, prepares and submits a First Payment Request in the ERP system, including:
        • Copy of the executed contract
        • ERP Navigation
        • Construction Project Module >>Payable Booking Process> Project Payable Booking
        • PM must specify the following among others.
        • Contract Type as Performance Certificate Based
        • 1st Payment amount
        • Net contract sum
        • The PM must attach relevant documents including 1st payment advance invoice from contractor.
        • The PM must select relevant BOQ summary Items while the system computes the relevant withholding tax as may have been set up, if any?
        • At submission, the transaction moves to the RQS for reviews
  5. Resident Quantity Surveyor (RQS) certification of completed works (measured works, milestone verification).
    • Any additional supporting documents (e.g., BOQ, advance payment guarantee, insurance certificates).
    • RQS validates bills and attaches relevant documents as deemed necessary.
    • RQS review, approves and submits for the attention of the Project Controller (CPC)
  6. Approval Process
    • The Project Director (PD) reviews the payment request for accuracy and completeness.
    • If compliant, the PD approves the request in the ERP system.
    • If non-compliant, the request is returned to the PM for correction
  7. Legal & Contractual Validation
    • Legal Officers verify:
      • The contract is duly executed.
      • Payment terms comply with the agreement (e.g., advance payment conditions, guarantees).
      • No legal impediments to payment exist
      • Once approved, the document moves to Internal Control Officer.
  8. Internal Control Officer
    • Internal Control verify:
      • The contract is duly executed.
      • Payment terms comply with the agreement (e.g., advance payment conditions, guarantees).
      • No legal impediments to payment exist.
  9. Pre-Payment Validation by Finance
    • The Project Accountant confirms:
      • The contract is registered in the ERP system.
      • All pre-payment conditions (e.g., bank guarantees, insurances) are fulfilled.
      • The payment amount aligns with the DoA limits
    • Group Project Finance Manager (GPFM) Responsibilities
      • Group Project Finance Manager (GPFM) review and validate all attached documents.
        • Subjective Final Approval – DOA
        • Approvals Limits
        • Less than N5 m– GPFM
        • Greater than – N5m – Chairman
      • At final approval, the system auto-creates the e-payment voucher for the approved net payable amount.
    • Construction Treasury Responsibilities
      • Project Accountant process e-payment vouchers and submits for cheque or transfer approval on ERP.
        • Bill Payment Approval
        • Project Accountant and Internal Control
        • GPFM and Zonal Internal Control
        • Zonal Internal Control Officer signs cheque and e-payment voucher on ERP at the same time
        • Zonal Project Accountant or GPFM signs cheque and e-payment voucher on ERP at the same time
  10. ERP Processing & Payment Release
    • Once all approvals are secured, the Project Accountant processes the payment in the ERP system.
    • The system enforces authorization limits and maintains an audit trail.
    • Payment is released to the contractor as per agreed terms (e.g., bank transfer).
  11. Compliance & Documentation
    • Delegation of Authority (DoA): All approvals must comply with the company’s DoA matrix.
    • ERP Archiving: All supporting documents (contracts, certifications, approvals) must be uploaded to the ERP for audit purposes.
    • Audit Trail: The ERP system logs all actions (submission, approvals, rejections) for transparency.
  12. Exceptions & Dispute Resolution
    • If discrepancies arise (e.g., incomplete documentation, non-compliance with contract terms), the request is escalated to the Finance & Legal Departments for resolution before reprocessing